In a functional tender, the client describes what the finished building must achieve and leaves the design, and with it many product choices, to the bidding contractors. For building product manufacturers, that moves the sales effort to the bidders' design and estimating teams during the tender period, and then to the winning contractor's detailed design after award. What helps the bidder is a product solution translated into the tender's functional requirements, with evidence and a price that arrive within the tender period.
This guide is for sales and technical teams at manufacturers. It explains what a functional tender contains in Germany and how the comparable principle works for public procurement under the UK Procurement Act 2023, how product decisions are made in this model, and a practical way to work with bidders. Legal references are as at 11 November 2026.
What a functional tender contains
In German public works, the functional tender is called a Leistungsbeschreibung mit Leistungsprogramm. Under § 7c VOB/A, and with matching wording under § 7c EU VOB/A 2026 above the EU thresholds, an authority can use it when it makes sense to put the design into competition together with the construction, in order to find the best technical, economic, design and functional solution.
The programme describes the building task, the purpose of the finished work and its technical, economic, design and functional requirements. It can include a model bill of items in which quantities are left fully or partly open. The bidder then submits more than a price: the design with a detailed explanation, a description of how it will build, and a structured description of the work, where required with quantities and prices for parts of it. If the bidder states quantities, it has to stand behind their completeness, either without restriction or within a tolerance set in the tender documents.
Because bidders do design work, § 8b EU (1) VOB/A 2026 says that where the authority asks bidders to prepare designs, plans, structural calculations or similar documents, in particular in § 7c EU cases, the tender must set an appropriate compensation, the same for all bidders. It is due to each bidder that has submitted, in time, a bid that complies with the tender and includes the required documents.
In the UK, for public procurement within the scope of the Procurement Act 2023, section 56 applies to competitive tendering procedures, awards in accordance with a framework and processes to join a dynamic market (subsection 1). Devolved Scottish authorities are excluded from the Act under section 2 (5) (a), according to Cabinet Office guidance. Section 56 (2) says procurement documents may not refer to design or a description of characteristics where they could appropriately refer to performance or functional requirements. For contracts where the contractor designs and builds, the JCT Design and Build Contract is intended for projects where the contractor carries out both the design and the construction work.
Who decides on products, and when
In a conventional tender, the client's planner writes a detailed specification, and the specification work happens during design, long before the tender. In a functional tender, much of that work happens inside each bidder's team during the tender period. Product decisions are shaped by the bidders' designers and estimators, within the client's requirements. After award, the winning contractor develops the detailed design and buys the packages.
Conventional tender with detailed specification | Functional tender | |
|---|---|---|
Who chooses products | Client's planner in the specification, contractor's buyer at purchase | Bidders' design and estimating teams, then the winning contractor's design and procurement |
When | Design stages before the tender | Tender period, then the contractor's detailed design |
What the client's documents contain | Items with defined properties | Purpose and functional requirements |
What helps a manufacturer | Specification texts during design | A solution mapped to the requirements, with evidence and price, during the tender period |
The client's planners still matter, because they write the functional requirements. A requirement that your product meets well only helps if it is written into the programme.
Exclusive project sales insights, directly to your inbox
Subscribe to our weekly newsletter.
A practical approach in five steps
1. Recognise functional tenders early. In German notices, look for Leistungsprogramm or funktionale Leistungsbeschreibung. In the UK, look for design and build procurement and requirements written in performance terms. Read the tender for what the bidder must design.
2. Know which contractors are pricing it. Ask the contractors you work with which functional tenders they are pricing, and offer support where your product fits.
3. Translate requirements into a solution. For each functional requirement that touches your trade, show which product or system meets it, the declared value, and the evidence. A bidder under time pressure needs a ready answer to the question of how to meet requirement X.
4. Price fast and reliably. The bidder's price depends on yours. Give a quote with the assumptions it is based on, including quantities, and say which parts are firm. Because the bidder has to stand behind its quantities, help it get them right.
5. Follow the project after award. The winning contractor develops the detailed design and can still change products. Keep in touch with its design manager and buyer until the package is ordered.
Treat all bidders the same
If you support several bidders on the same tender, give each the same technical information and the same price basis. That protects your relationships with all of them and keeps the competition fair.
Risks to watch
Late engagement. If you first hear about the tender in the last week, the bidders may have designed around another product.
Assumptions that do not hold. If your quote assumes a quantity or build-up the bidder later changes, the price no longer fits. Write assumptions down.
Changes after award. A product that appears in the winning bid can still be replaced during detailed design. Stay involved until the order is placed.
How Building Radar fits in
Building Radar tracks construction projects from early planning to tender. When a tender is published, Jeane, the intelligence inside Building Radar, summarises the tender documents. Whether a tender is functional, and which requirements concern your trade, your team still checks in the documents. See our tenders page.
Frequently asked questions
Is a functional tender the same as design and build? They share the idea that the contractor designs. The German Leistungsprogramm is a way of describing the work in a public tender. Design and build in the UK is a procurement and contract model, for example under the JCT Design and Build Contract.
Do bidders get paid for their design work? Above the EU thresholds in Germany, the authority sets an appropriate compensation, the same for all bidders, when it asks them to prepare designs and similar documents, in particular in functional tenders, under § 8b EU (1) VOB/A 2026. It is due to each bidder that has submitted, in time, a bid that complies with the tender and includes the required documents.
Can a bidder offer a variant in a functional tender? Above the EU thresholds, only where the notice allows variants. Below them, section 1 of the VOB/A applies where federal or state rules require it, and under section 1 variant bids are admissible unless the authority has declared that it does not allow them (§ 16 (1) No. 6). Our article on variant bids in this series explains the rules.
Where should a manufacturer start? With the contractors you already work with. Ask which functional tenders they are pricing and what they need from your trade.
Talk to us about finding projects early
If you want to discuss how your team finds functional tenders and design-and-build projects early, you can schedule an initial consultation.