After a contractor places an order, the project is not finished for the manufacturer. Deliveries are called off over weeks or months, the site programme moves, and quantities or details change. Run this phase with a clear process: a handover from sales to the order or project team, a call-off plan agreed with the contractor, a fixed contact for deliveries, a documented route for changes, and a short close-out at the end. The aim is that the products arrive as ordered and approved, and that the contractor wants to work with you again.
This guide is for sales, inside sales, order management and logistics teams at building product manufacturers. It describes a process your own team runs. How changes are priced and approved depends on your contract with the buyer, so check your terms and involve your commercial or legal team where needed.
Step 1: hand over from sales to the project team
The salesperson knows the history: the specification, the approval, the agreed prices and what was promised. The order or project team will handle the deliveries. Hand over in writing, with at least:
Item | Content |
|---|---|
Order basis | Order number, quote version, agreed prices and terms, validity |
Scope | Products, variants, quantities, and what is not included |
Approved documents | The approved submission pack and samples, with revision numbers |
Programme | The site programme as known, with phases and key dates |
Site logistics | Delivery address, access, unloading, storage, delivery time windows |
Contacts | Buyer, site manager, installer, planner, and who may call off deliveries |
Commitments | Anything promised beyond the order, such as site support or training |
Risks | Open points, such as unclear quantities or tight lead times |
Hold a short handover call. Agree who on your side is the contact for the contractor from now on, and tell the contractor.
Step 2: agree the call-off plan
Ask the contractor how it wants to call off deliveries and plan with them:
Which quantities are needed for which phase, and by when?
How far in advance will each call-off be sent?
Who on the contractor's side may call off, and by which channel?
What are your lead times per product, and what happens with short-notice call-offs?
Write the plan down and share it with your logistics or production planning. Review it when the site programme changes.
Step 3: coordinate each delivery
For each delivery, confirm the details before dispatch: date and time window, quantities, delivery address and unloading, and the person receiving it on site. After delivery, record what was delivered and any issues, such as damage or missing items.
If a delivery will be late or incomplete, tell the contractor as soon as you know, with the reason and a new date. An early warning gives the site time to adjust.
Exclusive project sales insights, directly to your inbox
Subscribe to our weekly newsletter.
Step 4: handle site changes through one route
Changes on site can arise, for example new quantities, a different variant or a changed detail. Handle every change request through one documented route:
Record the request. Who asked, what exactly, for which part of the building, and by when.
Check the effect. Does the change affect the approved submission, the price, the lead time or the installation? Involve your technical team if the product or build-up changes.
Confirm in writing. Send the contractor what the change means for price, delivery and approval, and get a written confirmation before you act.
Update the documents. Update the order, the call-off plan and, if needed, the approval documents.
A change to an approved product may need a new approval by the design team. Raise this with the contractor before delivery, as described in our article on the product approval workflow in this series.
Verbal agreements on site are easy to forget. A short written confirmation protects both sides.
Step 5: keep a regular rhythm
Agree a regular check-in with the contractor's buyer or site manager, at a frequency that fits the project. Use it to review the next call-offs, open changes and any issues. Keep the notes in your CRM against the project.
Step 6: close the project
When the last delivery has arrived, close the project deliberately:
Reconcile delivered quantities with the order and the changes.
Hand over the documents the contractor needs for its own handover, such as declarations of performance or maintenance information.
Ask for feedback on products, deliveries and communication.
Ask whether the project can be used as a reference, and record the permission status. Our article on building a reference project library in this series describes the fields.
Record lessons learned for the next project with this contractor.
A post-award checklist
Written handover from sales completed and contact named?
Call-off plan agreed and shared with logistics?
Delivery details confirmed before each dispatch?
Every change request recorded, checked and confirmed in writing?
Approval impact of changes checked?
Regular check-in with the contractor scheduled?
Close-out completed, documents handed over, feedback and reference permission recorded?
How Building Radar fits in
This process runs in your own team and systems. Our website does not describe site or delivery monitoring, and we do not claim it here. According to our features page, it connects new project data to existing deals and sends updates to the right team member, and it integrates with CRM systems including Salesforce, HubSpot, Microsoft Dynamics and C4C SAP. That can help your team keep project information and contacts in one place alongside the order.
Frequently asked questions
Who should own the project after the order? Name one contact on your side, for example from order management or project support, with sales informed. Tell the contractor who it is.
How do we handle short-notice call-offs? Agree in advance what lead times apply and what you can do at short notice. Confirm what is possible before you commit.
What if the contractor asks for a change on site by phone? Record it, check the effect and confirm it in writing before you act.
Why close out a project formally? It confirms quantities and documents, gives you feedback, and is the right moment to ask about a reference.
Talk to us about project-based sales
If you want to discuss how your team connects new project data to existing deals, you can schedule an initial consultation.